Replacement of Oyster Creek Prominent in State's Energy Master Plan
Oyster Creek's capacity must be replaced; township continues to push for a new generation facility in Lacey
Oyster Creek Generating Station is no footnote in the state’s Energy Master Plan as the final draft discusses the importance of replacing the nuclear plant’s capacity upon its closure in 2019.
With the inclusion of Lacey Township in the master plan, the Board of Public Utilities (BPU) is encouraging the state to replace Oyster Creek’s generation, board spokesperson Greg Reinert told Patch in August.
“There are a number of good reasons to locate a new plant on the Lacey Township property, including the presence of a highly skilled workforce, community support for such an initiative, and the existing electrical transmission infrastructure,” the plan states.
Reinert emphasized that the plan encourages the state to replace the station’s generation, not the plant.
“The EMP only talks about energy and where it comes from and does not propose a new plant,” Reinert said, although he noted that the BPU encourages Oyster's replacement.
“There’s no way to say where it’s going to be built,” he said. “Generation is deregulated. We can’t order generation to be built necessarily. Someone would have to be interested in building generation there… We’re working with those interests.“
The retirement of the plant will present the state with a challenge and its location prevents “significant transmission bottlenecks and overloads,” the plan says.
When a power plant closes, there is usually an increase in wholesale energy and capacity prices, the plan states. Also, at least $100 million in transmission upgrades will be required in order to transfer energy to the region, Reinert said.
The state is currently in the planning process to explore how to replace Oyster Creek.
Lacey Committeeman David Most continues to work with Congressman Jon Runyan, the Department of Environmental Protection (DEP) and the BPU on the possibility of building a new generation facility in the township.
"I am pleased that Gov. Christie recognized Lacey as an ideal community for a new plant,” Runyan said in an e-mail. “I have and will continue to work with the Board of Public Utilities, the Department of Environmental Protection, and Lacey officials to help bring Lacey Township a new power plant. Safe nuclear energy should remain a part of our nation's energy policy."
Most has meetings lined up with an Energy Coalition and the state, he said.
“It is happening as we speak with the DEP and BPU,” Most said. “We want to ensure that we have a setting at the table as far as an opportunity to build future generation here. We’re fighting the fight.”
It would be disingenuous to have the taxpayers subsidize a new infrastructure when Lacey already has it in place, he said.
“It’s very important that we look at it because there’s a lot of revenue at stake,” Most said. “It only makes business sense to create revenue and jobs and to keep generation in state.”
The energy tax receipt that Lacey receives for hosting Oyster Creek was cut by $1 million in the past few years, he said. The township currently receives more than $11 million in energy tax receipts, which makes up 40 percent of the budget’s revenue.
The township is also in the process of incorporating the land behind Oyster Creek into the Master Plan.
The current Master Plan does not encompass that property, Most previously said. The township is seeking to build a new plant on that property once Oyster Creek Generating Station shuts down in 2019 but currently, it is not zoned for that purpose.
Once the property is zoned properly, the township can begin the permit process with the Department of Environmental Protection and other agencies, Most said.
Determining the Future of Nuclear Energy
The state’s Energy Master Plan also calls for an in-depth look at nuclear power as it relates to the disaster at the Fukushima Daiichi plant in Japan.
“The events in Japan represent a siren for redoubled vigilance and federal regulatory oversight regarding the safety of all nuclear reactors in the U.S.,” the plan states.
New Jersey needs to continue its assessment of how nuclear power fits into its resource mix, the BPU says in the plan.
“The plan does not endorse building new nuclear at all,” Reinert said. “The plan talks about nuclear being a part of the mix. There are so many issues to building a new nuclear plant that that would be years away if that was even the route the state would go.”
According to the plan, if the state does not pursue additional in-state nuclear generation, the current greenhouse gas reduction goals will be unattainable.
“Vexing economic, safety, and environmental questions have to be answered before the State can embark on or abandon the path of developing the next generation of nuclear power plants,” the plan says.
The disaster at Fukushima has plagued Oyster Creek, as the plants are similar in design.
Jeff Tittel, President of the New Jersey Sierra Club, sees Fukushima as a "wakeup call."
“I think Fukushima is a wakeup call in coastal areas that nuclear power plants are not safe because we can’t necessarily control what happens with nature,” he said.
The Nuclear Regulatory Commission (NRC) continues to move ahead with the implementation of the Japan Task Force recommendations to be carried out “without delay,” spokesperson Neil Sheehan said. The NRC has several meetings lined up to discuss the implementation of recommendations.
“In short, the NRC is focusing many resources on addressing those areas found by the agency's Japan Task Force to be most pressing. A significant amount of work lies ahead in terms of the near-term recommendations,” he said.
The NRC will also study the long-term implications of the reactor events a Fukushima, Sheehan said.
“While all this work is taking place, the NRC has found the U.S. nuclear power plants safe for continued operation,” he said.
As for new nuclear plants, the NRC is reviewing an application submitted by PSEG for the Salem/Hope Creek site in New Jersey, he said. If approved, the company could bank the site and submit a separate application to build a new reactor or two.
But Tittel thinks the state is “heading in the wrong direction,” he said.
“Nuclear power is extremely expensive and not cost-effective,” he said. “There are big issues with safety and waste.”
The Energy Master Plan encourages the state to continue its coordination with the U.S. Department of Energy to accelerate a federal solution to the problem of storing radioactive waste.
“There is no federal solution. Those are just words that have no meaning,” he said. “Yucca Mountain [the former site for a federal nuclear repository] isn’t going to happen. Nuclear waste will be stored on site for generations.”
The Energy Master Plan “shifts the focus away from energy efficiency and renewable energy,” he said. The plan emphasizes the need for fossil fuel and nuclear energy.
“New Jersey could easily meet their energy needs through energy efficiency and renewable energy. Energy efficiency is the most cost effective way to save on energy demands and the need to build new plants,” he said.
If a new generation facility is built in Lacey Township, it will inevitably impact the Barnegat Bay, he said.
The BPU recommended a state agency panel be established to assess the role of nuclear energy in the New Jersey’s future.
Tim O'Connor
5:46 pm on Thursday, December 8, 2011
All's we here is we talked with the state or our politicians? Let me point out corporations build plants not the state or politicians! When are you going to get it? Where ever a plant is built will impact the bay, so that point is just dumb. We need to have a real economic development committee. A group out talking with corporations who would actually build something.
The infrastructure is here and currently exists. The largest way to minimize the impact is to not create a new area of destruction. It's not just the infrastructure but the security force and measures also currently exist. Moving to another location will only drive up costs in this area because security will remain in force here for years too!
Stop playing politics and focus on the obvious. Find a corporation who will come to Lacey or maybe Ocean Township will build a new plant on their side of the Forked River in Ocean Township and have there municipal tax rate subsidized.
tr
6:24 pm on Thursday, December 8, 2011
Offer tax breaks, on a temporay basis, to plant employees, who live in Lacey, if they give back salary and benefits to keep a power generation plant in Lacey.
Jack
8:07 am on Friday, December 9, 2011
Who would want to do business in New Jersey now after seeing how NJ politicians pander to fanatics like Jeff Tittel? Here we have a nuclear power plant that was built and paid for 40+ years ago that has not killed, injured, or made sick a single member of the public in more than 4 decades of continuous operation and yet Jeff Tittel and the beaurocrats in Trenton have managed to close the plant citing imaginary environmental concerns. Who would spend billions on a new facility just to have some activist with high priced lawyers shut them down?
Has anyone seen the people lined up elbow to elbow on the Rt 9 bridge this past week? It's December, what are they doing there fishing? I thought Oyster Creek was supposed to be some environmental menace, so why would there be fish there in December? Are those fisherman wrong or is Jeff Tittel just afraid of nuclear power? Ask yourself again in 2019 when your electric bill starts to go up.
LT Guy
10:28 am on Friday, December 9, 2011
Gee Jack, you sound an awful like Dave Most did until election season got here. "No one will come to New Jersey to build a plant with the Environmental "wackos" here" to paraphrase. Now all of a sudden he and our brilliant Congressman are working feverishly on something we knew was coming inevitably for years. People are asking NOW, what action are you taking to address this issue, and all the answers they are getting is (to paraphrase again) "it's being discussed in smokey back rooms". How about some transparency for a change. To me, that answer is the same as "we're not doing anything", which is probably what the case is. It's good to know our "elected" officials are working hard for us..
Peter Mulshine
1:29 pm on Friday, December 9, 2011
Oyster creek Takes water out of the bay &HEATS IT,,THEN the fish die off when the reactor shtus down.WHEN Oyster creek fails,,you will see what a disaster it is.We can fix it w/ solar plants on the roofs of every mall in NJ,,when the sun is blindingly bright,,,maximum input will also be producing electricity that will not be bought from OUTSIDE of NJ ,,the $$$ will stay here.
Tim O'Connor
1:09 pm on Friday, December 9, 2011
It appears the residents need to conduct a study as to the size, shape, markets that can build out the power plant property and remaining industrial park site. What type of industries are available and what are we willing to host here in Lacey is the question? Watch the exchange between the TC and myself on TV21 from last nights meeting. Mr. Most stated it is up to the state to decide? Also, don't worry they will take care of everything? Now that is scary!
LT Guy
1:14 pm on Friday, December 9, 2011
You sure got that right Tim. The State couldn't find their own (explitive deleted) with two free hands and a flashlight in their mouth. We're going to rely on them to take care of Lacey? I don't think so.
Tim O'Connor
1:33 pm on Friday, December 9, 2011
@Peter, the state has already mandated, what ever gets built will require cooling towers. Hot water not is not an issue!
Sean Conneamhe
1:46 pm on Friday, December 9, 2011
"No Nukes, please."
patricia doyle
1:56 pm on Friday, December 9, 2011
Sean - I think you better start going to the meetings. Last night, Mr. Most stated that "everyone in Lacey wants another nuclear plant."
Energizer Bunny
3:48 pm on Friday, December 9, 2011
NIMBYs I have a question for those of you who oppose nuclear energy, why did you move here? Was it because of the low municipal taxes due to the power plant? Was it for a job as the town and school system grew? Was it for the opportunity that Lacey had to offer for small businesses? If you are opposed to a new plant in Lacey, I wonder if you also opposed the windmills at Wal Mart? A new nuclear plant would be the best form of electricity. However, the TC blew it when they had the opportunity and leverage to attract such a plant. The proposed solar farm is a joke, not only inefficient and must be subsidized by the taxpayers. The environmentalists will oppose it like they opposed the Mojave Desert Solar Power only this time it will be the timber rattlers, turtles, birds etc… won’t be able to warm themselves or build their ground nest. If you are opposed to a new plant I suggest you turn off your lights, AC, heat, refrigerators, TVs and unplug your electric cars.
joe smith
5:08 pm on Friday, December 9, 2011
as long as tittle is around we all will be living at little house on the prairie. turn off all lights, heat, gas, oil, everything!!!!!!!!!!!!!! he is against everything and everything!!!!!!!!!!!! totally ridiculous. i am an avid hunter and fisherman but oc did not totally ruin the bay and the surrounding area, thats that. 40 years ago all was fine 30 years ago all was fine. lets look at overbuilding, fertilizer, pollution runoff into the bay from overbuilding, (no water shed) if you know what that means, yes the plant could use cooling towers but that is another super large animal in itself!!!!!!!! wait and see the ramifications from them. salem 1/2 and hope creek are prime examples. there are major problems with both systems but we still need nuks, thats that.
Tim O'Connor
5:25 pm on Friday, December 9, 2011
For the record, I am 100 % behind building a new nuclear plant here in town. I moved to Lacey and spent a year working on the Forked River Nuclear Generating Station until the plant shut down in '79. I worked at over 14 different nuclear plants throughout the country. My position is based on reality and would remain very doubtful a new nuclear plant could be approved. Therefore focus our efforts on a gas fired plant. O by the way, I also worked at 6 gas and oil powered plants.
Energizer Bunny
5:27 pm on Friday, December 9, 2011
Maybe Tittle should talk with Patrick Moore co-founder of Greenpeace. Moore was a co-founder of Greenpeace who currently co-chairs an industry-funded initiative, the Clean and Safe Energy Coalition, which supports increased use of nuclear energy. Moore says that his views have changed since founding Greenpeace, and he now believes that using nuclear energy can help counteract catastrophic climate change from burning fossil fuels. Says Moore, "The 600-plus coal-fired plants emit nearly 2 billion tons of CO2 annually -- the equivalent of the exhaust from about 300 million automobiles." Moore also cites reports from the Clean Air Council that coal plants are responsible for 64 percent of sulfur dioxide emissions, 26 percent of nitrous oxides and 33 percent of mercury emissions.
"Meanwhile, the 103 nuclear plants operating in the United States effectively avoid the release of 700 million tons of CO2 emissions annually," says Moore. "Nuclear energy is the only large-scale, cost-effective energy source that can reduce these emissions while continuing to satisfy a growing demand for power. And these days it can do so safely." Moore points out that the average cost of producing nuclear energy in the United States was less than two cents per kilowatt-hour, comparable with coal and hydroelectric. He predicts that advances in technology will bring the cost down further in the future.
joe smith
7:22 am on Saturday, December 10, 2011
good job energizer bunny. most of the coal plants are going to be forced to shut down soon anyway so the only choice is nuks but like my last post do your homework on the cooling towers, they are actually just as bad or worse. i would love to post some of the articles i have on energy sources but they are like 100 pages long. covers all power and pros and cons. tim a gas plant would be ideal but i believe it is already going to be built in west depford by LS power, 738 mw starting 1st quarter next year.
Tim O'Connor
10:22 am on Saturday, December 10, 2011
This state needs more than one plant to be built. Many plants are setting old and the time line to get something built is years! If for no other reason newer plants with improved technology will generate power with less pollution.
tr
5:10 pm on Monday, January 9, 2012
If the current locations of nuclear power plants, in the continental United States of America, is the only place in the entire country where spent fuel rods can be stored, then the federal government should stipuate to the energy industry that these are the only sites in the entire country where a nuclear plant can be operated. Either upgrage to newer and safer plants at current locations or get out of the business. Why let big industry possibly contaminate virgin land with new sites? The industry will fight over current locations where infrastrucure, security, storage, and evauation systems are alrady in place. The majority of the people living around the current sites made the consicious choice to live there. Why expose more citizens to possible danger against their will if unnecesary?